M80 Ring Road Upgrade Sydney Road to Edgars Road



Overview

Vic Piling partnered with CPB contractor for the construction of piles for M80 Blaxland Avenue Overpass. This included upgrading the cycling and pedestrian bridge and construction of 1200 mm diameter and 8 m deep piles. Difficulties in this project included the disposal of large quantities of spoil in a restricted area, and having to hang such large cages, without having to resort to the use of a crane. In a separate exercise, 750mm diameter and 6m deep piles were installed under the gantry structures along a 2 km stretch.

 

Details

Location

Blaxland Avenue

Client

AECOM, CPB

Expertise

Construct Only

Partners

Major Road Projects Victoria

About us

VIC PILING install bored piers from 300mm to 2100mm diameter and up to 40m deep. We have most efficient tools to drill rock and even granite. We are capable to install screw pile up to 1050mm diameter and 45m deep.

Address

48 Cambria Road, Keysborough, VIC 3173

Contact Detail

Where to find us