Newport Power Station Gas pipeline upgrade

Gallery not found.



Overview

Newport Power Station Gas pipeline involved construction of retention systems and laying of new pipelines. Vic Piling has constructed bored piers 600 mm diameter up to 5m deep into a hard layer of basalt rock. It was challenging to drill holes next to existing gas pipelines without disturbing their integrity. To ensure this, vibration monitoring devices were used.

 

Details

Location

Newport

Client

National Australian Pipeline

Expertise

Construct Only

Partners

APA